SH1 Ngutukaka, Otago, South Island

January 1, 2001

This project was a realignment valued at $1.8M and involving 2 km of pavement construction, 100,000m3 earthworks, multiplate culvert structures including a 3.2m diameter multiplate culvert and 2.7m diameter Helcor stock underpass.

Construction started in March 2000 and finished in October 2000.